Our Road Department is getting ready for your Summer road work. As funds are available, the below list of roads represents the maintenance schedule this year.

The following work is planned for the summer of 2016:

Chip & Seal

Palm Road & Saxe Road from Randolph Road to Ranfield Road, 1.3 miles

Steffy Road from Congress Lake Road to Griggy Road, 1.3 miles

Griggy Road from Waterloo Road to Pontius Road, 1.6 miles

Manning Road from Mishler Road to Heimbaugh Road, .6 miles

Woodsdale Drive, entire length, .6 miles

Deer Crossing, entire length, .25 miles

Deer Run Circle, entire length, .15 miles

 

Paved

Palm Road from Randolph Road to Trares Road

 

While this is the plan for 2016 road maintenance, there may be some changes, dependent on the actual cost of repaving Palm Road.  Chip & Seal will be done by the Suffield Road Department.  Repavement of Palm Road will be done by a private contractor, to be determined by bids submitted and opened on July 12, 2016.